Border Fencing between the UK and France

IMPROVING PERIMETER SAFETY AND SECURITY AT THE EUROTUNNEL

Jacksons were on site the following day for a detailed briefing and to survey the project, following which the company responded quickly and had returned its tender submission for review by the principal stakeholders (Eurotunnel as the client and Border Force on behalf of the UK Government), complete with wind loading and foundation calculations, within 1 week from the date of the initial visit.

Two contractors were appointed to the project for 5km of fencing and associated gates to be completed by the end of October. Around 80% of the new fencing would be deployed to reinforce existing physical security measures with additional layers, while the remaining 20% was destined to replace existing fencing.

Initially Jacksons were awarded 3.3km of the 5.0km contract, however as of October 2016, the company worked across 4 key locations spread throughout the perimeter and interior of the site and installed a total of 1

https://www.jacksons-security.co.uk/case-studies/improving-perimeter-safety-and-security-at-eurotunnel-in-calais

Fencing protecting the main rail line into the channel tunnel

Company details

Incorporated:
10 July 1967
Industry:
Ports and logistics
Thank you and your teams for your key contribution to the success of our security plan. We have fully appreciated the commitment and the efficiency of your teams …The new fencing and other security upgrades have made a big difference to the security at our terminal and allowed our staff and security services to operate in greater safety in what are difficult times.”