The main items of Work of this Contract include the following: .1 Demolition and removal of existing Clarifier Unit-1 parts. .2 Installation of new Clarifier Unit components and associates drives and controls. .3 PLC and SCADA system upgrading. .4 Miscellaneous chemical system upgrades. The Site of the Work of this Contract is located at the following locations:.1 Westlock Regional Water Treatment Plant